Skip to main content

Living Breakwaters Construction Updates

Living Breakwaters Construction Updates

Living Breakwaters Construction Update - December 2021

DECEMBER 2021 UPDATE

 

As the holidays are approaching, the contractor is on track to finish the base layers of Breakwater ‘A’, ‘B’, ‘C’, and ‘D’ by the end of this year. Placement of these four breakwaters’ marine mattresses have been completed. Currently, the heavy geotextiles layers on Breakwater ‘C’ and ‘D’ are being installed. Early next year, the contractor will start placing stones on top of the base layer of Breakwater A. You will begin to see the emergent portion of this breakwater next spring! The production of stone at Carver Quarry and casting of Precast Ecological Concrete units at New Jersey Precast Plant are also ongoing.

Moreover, the contractor maybe working on some Saturdays from now until the end of the year to make up for the shorter holiday work weeks. Please check back on this page for the latest information on when those dates will be.
 
Wednesday, December 15, 2021

 

CONSTRUCTION SCHEDULE

Living Breakwaters construction timeline

 

The breakwaters will be constructed from the southwest to the northeast (see plan below) between the summer/fall of 2021 and the end of 2024. The shoreline restoration component will be constructed in the final season of construction (2024).

Project Timeline Details

Design

Start Date: Summer 2015
Completion Date: Fall 2019

Procurement

Start Date: Winter 2019
Completion Date: Winter 2020

Construction

Start Date: August 2021
Projected Completion Date: Fall 2024

Funding

Total Funding: $107,000,000

Sources

  • HUD Community Development Block Grant – Disaster Recovery $60,000,000
  • New York State - $47,000,000

Includes Funding for:

  • Design/Permitting/Planning
  • Construction and Administration
  • Social Resiliency Programming

 

NAVIGATION SAFETY FOR LOCAL MARINERS DURING CONSTRUCTION

Breakwater construction will generally proceed from the southwest, where the first breakwater will be installed, to the northeast. Partially constructed breakwaters may or may not be visible above water. Construction barges will be moored in the vicinity of the construction zone and will be marked with lights on four corners. Anchors will also be marked with lighted buoys. During work hours, divers will be present in the water. Mariners and recreational craft should avoid this area and keep their closest point of approach at least 0.5 nautical miles (3,308 feet) from buoys, lighted posts, and barges. Please refer to the Local Notice to Mariners for more information.

Living Breakwaters Project Area

QUESTIONS?

Visit the frequently asked questions page.
Still have questions? Email [email protected]
For press inquiries contact [email protected]

Project Staff

Project liaison: Scott Narod
Contact GOSR about this project.

Location

Tottenville, Staten Island
Shoreline between Brighton Street End and Page Avenue

Back to project home