Living Breakwaters Construction Update - December 2021

DECEMBER 2021 UPDATE

 

As the holidays are approaching, the contractor is on track to finish the base layers of Breakwater ‘A’, ‘B’, ‘C’, and ‘D’ by the end of this year. Placement of these four breakwaters’ marine mattresses have been completed. Currently, the heavy geotextiles layers on Breakwater ‘C’ and ‘D’ are being installed. Early next year, the contractor will start placing stones on top of the base layer of Breakwater A. You will begin to see the emergent portion of this breakwater next spring! The production of stone at Carver Quarry and casting of Precast Ecological Concrete units at New Jersey Precast Plant are also ongoing.

Moreover, the contractor maybe working on some Saturdays from now until the end of the year to make up for the shorter holiday work weeks. Please check back on this page for the latest information on when those dates will be.
 
Wednesday, December 15, 2021